A construction lien Florida law gives to unpaid contractors, subcontractors and suppliers can stop a sale or a refinance cold. The lien attaches to the land itself, so it follows the property and not the person who ordered the work. However, the statute also sets strict deadlines, and a lien that misses one can fail. This guide explains who may claim a lien, each deadline in chapter 713, how an owner can shorten or remove a lien, and what happens when one turns up before closing.

What Is a Construction Lien in Florida?

A construction lien is a claim against real property for unpaid labor, services or materials that improved it. Part I of chapter 713 of the Florida Statutes carries the name Construction Lien Law. Older documents call the same claim a mechanic's lien.

The idea is simple. For example, a roofer who replaces your roof has added value to your home. If nobody pays the roofer, the law lets the roofer look to the property for payment. As a result, an unpaid bill can become a recorded claim in the county's official records.

That claim matters to everyone who deals with the property later. A buyer does not want to inherit it, and a lender will not lend behind it. So the lien has to be paid, released, bonded, discharged or expired before the title can be insured without an exception for it.

Who Can Claim a Lien Under Chapter 713?

Chapter 713 sorts lienors into groups. First, a contractor who deals directly with the owner is "in privity" with the owner and has lien rights under section 713.05. Next, subcontractors, sub-subcontractors, laborers and material suppliers get their rights under section 713.06, even though they have no contract with the owner. In addition, architects, landscape architects, interior designers, engineers, and surveyors and mappers can claim a lien for their professional services under section 713.03.

The second group surprises many owners. You may pay your general contractor in full and still face a lien from a supplier the contractor never paid. In fact, the warning printed in the statute says that some unpaid parties can file liens against your property even if you have made payment in full.

There are limits, however. A contractor, subcontractor or sub-subcontractor who is unlicensed under Florida's contractor licensing laws has no lien rights at all. Also, when the direct contract price is $2,500 or less, the job is exempt from every part of the lien law except the section for those who contract directly with the owner.

The Notice to Owner Comes First

Most lienors who did not contract with the owner must warn the owner early. They do it with a document called a notice to owner. Under section 713.06, the lienor must serve it before starting or within 45 days after first furnishing labor, services or materials. It must also arrive before the owner pays out the final payment on the strength of the contractor's final payment affidavit.

Missing that deadline is fatal. The statute says that failure to serve the notice on time is a complete defense to the lien. Laborers are the exception, because they do not have to send one.

The notice itself is not a lien, and the statute says so. Instead, it tells the owner who is working on the job. Then the owner can collect a lien release from that party before paying the contractor. An owner who pays this way makes what the statute calls proper payments and generally avoids paying twice.

The Claim of Lien and the 90-Day Deadline

The claim of lien is the document that creates the recorded lien. A lienor records it with the clerk of the circuit court in the county where the property sits. Under section 713.08, the lienor may record it during the work or afterward, but no later than 90 days after the final furnishing of labor, services or materials.

The claim must be sworn. It names the lienor, the party who hired the lienor and the owner. It also describes the work, the property, the first and last dates of furnishing, and the amount unpaid. Next, the lienor must serve the claim on the owner before recording or within 15 days after recording. Late service can make the lien voidable to the extent the delay harmed someone entitled to rely on it.

Here are the main deadlines in one place.

StepDeadlineFlorida Statutes
Notice to owner servedBefore starting, or within 45 days after first furnishing713.06(2)(a)
Claim of lien recordedNo later than 90 days after final furnishing713.08(5)
Claim of lien served on ownerBefore recording, or within 15 days after713.08(4)(c)
Lawsuit to enforce the lienWithin 1 year after recording713.22(1)
Lawsuit after a notice of contestWithin 60 days after service of the notice713.22(2)
Response to a summons to show causeWithin 20 days after service713.21(4)

You can read each section in chapter 713 of the Florida Statutes.

When Does the Lien Attach to the Property?

Priority is where a construction lien in Florida differs from most other liens. A mortgage or judgment usually ranks from the day it is recorded. By comparison, the liens of contractors, subcontractors and suppliers attach and take priority as of the recording of the notice of commencement. If no notice of commencement was recorded, they rank from the day the claim of lien is recorded. Liens for professional services always rank from the recording of the claim.

So a lien recorded in June can reach back to a notice of commencement recorded in January. That reach-back is why lenders and title agents care so much about open notices. Our guide to the notice of commencement in Florida explains that document and how to terminate it, so we will not repeat it here.

How Long Does a Construction Lien Last?

A lien under the Construction Lien Law does not last forever. Under section 713.22, it continues for one year after the claim of lien is recorded. It survives longer only if the lienor files a lawsuit to enforce it within that year. An amended claim that shows a later date of final furnishing restarts the one-year clock from its own recording.

Even a timely lawsuit has a catch. The lien is not enforceable against later buyers and creditors without notice unless the lienor also records a notice of lis pendens.

construction lien Florida

An owner does not have to wait out the year. First, the owner can record a notice of contest of lien with the clerk. The clerk serves it on the lienor, who then has 60 days from service to file suit. Otherwise, the statute says the lien is extinguished automatically.

Second, any interested party can file a complaint in circuit court under section 713.21. The clerk then issues a summons that gives the lienor 20 days to show cause why the lien should not be enforced or cancelled. If the lienor fails to respond or to sue, the court orders the lien cancelled.

Finally, chapter 713 punishes inflated claims. A lien that willfully exaggerates the amount due is a fraudulent lien under section 713.31, and a court that finds one must declare it unenforceable. Because the prevailing party in a lien suit recovers attorney fees, talk to a Florida construction attorney before you contest a lien.

Transferring a Lien to a Bond or Cash Deposit

Sometimes an owner disputes the amount but needs the property free now. Section 713.24 offers a way out. Any person with an interest in the property can transfer the lien to other security. That person either deposits cash with the clerk or files a bond from a licensed surety.

The statute sets the amount. It equals the amount demanded in the claim of lien, plus interest at the legal rate for three years, plus the greater of $5,000 or 25 percent of the amount demanded. That last piece covers attorney fees and court costs.

Once the clerk records the certificate of transfer, the lien no longer burdens the real property. The lienor's claim continues, but against the bond or the cash instead of the land. As a result, the sale or loan can go forward while the dispute plays out in court.

How Is an Open Construction Lien Handled at a Sale or Refinance?

The title search finds a recorded claim of lien, because the clerk indexes it under the owner's name. The lien then appears on the title commitment as a requirement that someone must satisfy before closing. In practice, there are four common ways to clear it.

First, the seller can pay it. The closing agent requests a payoff figure, pays the lienor from the seller's proceeds and records the release. Under section 713.21, the lienor signs the release before a notary, and the release cites the recording information of the lien.

Second, the owner can transfer a disputed lien to a bond or a cash deposit, as described above. Third, the owner can use a notice of contest to force the issue in 60 days. Fourth, a lien more than a year old may have expired. Still, the agent checks the court records for a lawsuit and a lis pendens before treating it as dead, and the underwriter has the final say.

Unrecorded Lien Rights and the 90-Day Affidavit

Unrecorded lien rights are the harder problem. Work finished last month may not have produced a claim of lien yet, since the lienor has 90 days to record one. For that reason, the standard Florida residential contract asks the seller for an affidavit that no improvements or repairs were made in the 90 days before closing. If work took place, the seller delivers releases or waivers from every contractor, subcontractor and supplier.

The title agent relies on that affidavit, too. With it, the agent can usually remove the standard exception for unrecorded construction liens from the policy. A buyer of a newly built home should expect closer review, as our guide to new construction closings explains.

A refinance works the same way. The new lender wants its mortgage in first position. Therefore, the agent has to clear a recorded lien, or a notice of commencement that could give later liens priority, before the loan closes.

What Owners Can Do Before a Lien Appears

Good paperwork during the job is the cheapest protection. First, hire licensed contractors, and keep every notice to owner you receive. Each one names a party who can lien your home.

Next, ask for a lien release with each payment. Florida law does not let a lienor waive lien rights in advance, but a lienor can release them for work already furnished. The statute even supplies the forms for progress payments and final payment.

Then, before you make the final payment, get the contractor's final payment affidavit. The law tells the owner to hold the final payment until the contractor furnishes it. Keep those records, because your closing agent will ask for them if you sell within a few months.

Remember that this lien is different from a city or county lien. Code enforcement fines and unpaid utility bills come from local government, and a municipal lien search finds those. Likewise, our comparison of a lien search and a title search shows which search catches which problem.

Bottom Line

A construction lien Florida owners discover before closing is usually fixable, but the fix depends on dates. The lienor has 45 days for the notice to owner, 90 days for the claim of lien and one year to sue. Meanwhile, the owner can cut that year to 60 days, ask a court to cancel the lien, or move it to a bond.

Verified Title coordinates the title search and helps collect the releases and affidavits a file needs. Our partner agency, Atlantic Title Firm LLC, handles the closing and issues the policy. We are not a law firm, so ask an attorney about a disputed lien. If a lien or an open permit is holding up your sale, see our title curative services or open a title order to get the search started.

Frequently Asked Questions

How long does a construction lien last in Florida?

Under section 713.22 of the Florida Statutes, a construction lien lasts one year after the claim of lien is recorded unless the lienor files a lawsuit to enforce it within that year. An owner can shorten the period by recording a notice of contest of lien. The lienor then has 60 days after service of the notice to file suit, or the lien is extinguished.

How long does a contractor have to file a lien in Florida?

A lienor must record the claim of lien no later than 90 days after the final furnishing of labor, services or materials, under section 713.08. Subcontractors and suppliers who have no contract with the owner must also serve a notice to owner within 45 days after they first furnish work or materials, or their lien fails.

Can I sell my house with a construction lien on it?

Yes, but the lien must be dealt with before a title insurer will insure the buyer without an exception for it. The usual paths are paying the lienor at closing in exchange for a recorded release, transferring the lien to a bond or cash deposit with the clerk under section 713.24, or showing that the lien has expired or been discharged by a court.

Verified Title is not a licensed title insurance agency. Atlantic Title Firm LLC, a licensed Florida title insurance agency (FL DFS license W670036), provides all title insurance, closing, settlement and escrow services. You can verify the license on the Florida Department of Financial Services licensee search.