A notice of commencement in Florida is a short form an owner records before construction starts. It tells the world that work is about to begin, who the contractor is, and where to send lien notices. It looks harmless, but it has real effects on title. Construction liens can take priority from the date the owner recorded the notice, so an open notice shows up on every title search until someone deals with it. This guide covers the construction lien law behind it, when you need one, how long it lasts, and how title companies clear it before a sale or refinance.
How Florida's Construction Lien Law Works
Part I of Chapter 713 of the Florida Statutes is the Construction Lien Law. It lets contractors, subcontractors, suppliers and laborers who improve real property claim a lien on that property if they go unpaid. That is true even when the owner paid the general contractor in full. If the contractor never paid a supplier, the supplier may still have lien rights against the house.
To balance that risk, the law gives owners a set of protections. The notice of commencement is the starting point. Next come notices to owner, then the contractor's final affidavit and lien releases. When an owner follows the steps, the law limits how much the owner might have to pay twice.
You can read the notice of commencement statute, section 713.13, on the Florida Legislature's website.
What Is a Notice of Commencement?
The notice is a one-page form set out in the statute. It lists the property's legal description and address, a general description of the work, and the owner's name and interest. It also names the contractor, any surety on a payment bond, the construction lender, and a person in Florida who can receive notices. The owner may also name someone else to get copies of lien notices.
Only the owner can sign it. The statute says no one else may sign in the owner's place. Once signed, the owner records it with the county clerk and posts a certified copy, or a notarized statement that it went to the clerk for recording, at the job site.
Recording the notice does not create a lien. Instead, it gives notice that lien claims may follow and may take priority. That priority is why title companies care about it.
When Is a Notice of Commencement Required in Florida?
Two dollar figures matter. First, section 713.02(5) exempts any improvement with a direct contract price of $2,500 or less from most of the lien law. Small jobs simply fall outside it.
Second, section 713.135 governs building permits. When the direct contract is more than $5,000, the building department must require a copy of the recorded notice before the first inspection. If no copy is on file, the inspector may not approve later inspections. However, repairing or replacing an existing heating or air-conditioning system for less than $15,000 is exempt from that rule.
Timing matters too. The owner must record the notice before work actually begins. If work does not start within 90 days after recording, the notice becomes void. In that case, the owner records a new one.
A construction lender also has duties. Before it pays any construction money to the contractor, the lender must record the notice of commencement. A lender that skips this step can be liable to the owner for the resulting damages.
How Long Does a Notice of Commencement Last?
By default, a notice of commencement in Florida expires one year after recording. The form lets the owner choose a later date, and the statute requires a longer period when the contract runs more than a year. The owner can also amend a timely notice to extend it.
Expiration has a sharp edge. Payments the owner makes after the notice expires count as improper payments under the statute. So an owner who keeps paying a contractor on an expired notice can end up paying twice if a subcontractor files a lien. If a long job is still running near the one-year mark, extend the notice before it lapses.
Notices to Owner
Subcontractors and suppliers who do not contract directly with the owner must serve a notice to owner to keep their lien rights. Under section 713.06, they must serve it before they start or within 45 days after they first furnish labor, services or materials. They must also serve it before the owner makes final payment to the contractor. Laborers are exempt.
The statute requires strict compliance with that timing. A late notice to owner is a complete defense to that party's lien. For that reason, owners should save every notice to owner they receive. Each one tells the owner who else expects payment out of the job.
Before each payment to the contractor, the owner should confirm that the contractor has paid the people who served a notice to owner. Most owners do that by collecting a partial lien release from each of them.
The Contractor's Final Affidavit
When the final payment comes due, the contractor must give the owner a final affidavit. It states that the contractor has paid in full every lienor who served a notice to owner. Otherwise, it lists who is still unpaid and how much is owed.

The statute lets the owner hold the final payment until the contractor delivers the affidavit. Also, the contractor must deliver it at least five days before suing to enforce its own lien. So the affidavit protects both sides. The owner learns who is still owed, and the contractor cannot skip that step.
The owner may rely on the affidavit, except as to lienors who served a notice to owner and are missing from it. That exception is why title companies compare the affidavit against the notices to owner in the file.
Lien Deadlines for Contractors and Suppliers
A lienor must record a claim of lien no later than 90 days after its final furnishing of labor, services or materials. That deadline appears in section 713.08. The lienor must then serve a copy on the owner within 15 days after recording, if it did not serve one before.
A recorded lien does not last forever. Under section 713.22, it expires one year after recording unless the lienor files suit to enforce it. An owner can shorten that window. By recording a notice of contest of lien, the owner cuts the lienor's time to sue to 60 days from service of the notice. If the lienor misses that, the lien ends automatically.
An owner can also move a lien off the property by transferring it to a cash deposit or a surety bond. The court then treats the deposit or bond as the security for the claim, and the property is free to sell.
| Step | Deadline under Chapter 713 |
|---|---|
| Notice of commencement void if work has not started | 90 days after recording |
| Notice of commencement expires (default) | 1 year after recording |
| Notice to owner | Within 45 days after first furnishing |
| Claim of lien recorded | 90 days after final furnishing |
| Claim of lien served on owner | Within 15 days after recording |
| Lien expires without a lawsuit | 1 year after recording |
| Lienor's time to sue after a notice of contest | 60 days from service |
| Notice of termination takes effect | 30 days after recording, or later |
How Open Notices Affect a Sale or Refinance
An open notice of commencement shows up on the title search. Because liens can relate back to the date of the notice, a lien filed after closing could still claim priority over the buyer's deed or the new lender's mortgage. That is a risk no title insurer wants to take without proof that the owner has paid for a finished job.
As a result, the title commitment usually lists the notice as a requirement to clear. Our guide to reading a Florida title commitment shows where it appears. A refinance raises the same issue, because the new lender wants first priority. Our guide to refinance title insurance in Florida explains why the lender insists on that.
Sellers should also expect related questions. A municipal lien search shows whether the building department closed the permit behind the job. An open permit and an open notice often travel together.
How Title Companies Clear a Notice of Commencement
The usual path depends on whether the work is finished.
When the job is complete, the title company asks for proof that everyone has their money. That usually means the contractor's final affidavit, a final lien release from the contractor, and releases from each party who served a notice to owner. The owner then signs an affidavit stating that the work is complete and paid.
Many title companies also ask the owner to record a notice of termination under section 713.132. The notice must state that the owner has paid all lienors in full, and the contractor's final affidavit must go with it. The owner serves it on the contractor and on each lienor who served a notice to owner before recording it. It takes effect 30 days after recording, or on a later date it names.
That 30-day wait matters for timing. If closing is close, the title company may accept the affidavit and releases instead, or ask the underwriter to insure without the exception. Each underwriter sets its own requirements, so ask early.
When work is still in progress, the answer is harder. A buyer would be taking on a job that is not finished, so the parties usually wait or negotiate an escrow and releases. If a claim of lien is already recorded, the seller can pay it, contest it or transfer it to a bond before closing.
Practical Tips for Owners
First, record the notice before work starts, and post it on site. Next, keep a file of every notice to owner you receive. Then collect lien releases with each payment. Finally, get the final affidavit before you make the last payment, and record a notice of termination once you have paid everyone. Those steps also save time when you later sell or refinance.
Bottom Line
A notice of commencement in Florida starts the construction lien process and gives lienors a priority date. It lasts one year by default, and it stays on title until someone shows that the job is finished and paid. Before a sale or refinance, expect to provide the contractor's final affidavit, lien releases and often a notice of termination.
Verified Title reviews open notices of commencement on every file and tells you early what it needs to clear them, in all 67 Florida counties. If you have a closing coming up after recent work, open a title order and we will check the record right away.